Construction contracts are usually lengthy and complicated, composed of a wide range of documents In a perfect world, the contract provides the clarity and direction all stakeholders need to move forward on the project. Unfortunately, it’s not uncommon for contract documents to conflict with one another. For example, the drawing might specify one type of hardware for the doors, while the specs show another. And when contractors run into a conflict, how do they know which contract document to refer to?
Many contracts include a clause that lays out which documents take precedence, and in which order. This contract precedence clause provides clarity and serves as a useful tool if confusion arises. Let’s take a look at what contract precedence means: how it helps clear confusion, how precedence applies to different contract types — and alternatives to look at if dictating the order of precedence in construction contracts still leaves room for issues.
Table of contents
An order of precedence contract clause tells everyone involved in the project which documents supersede others. In some cases, the contract actually uses two clauses here. The first might simply state that contract precedence applies, while a sister clause lists out the order of precedence. In other contracts, these two clauses are combined into one.
Essentially, detailing the order of precedence in construction contracts provides a tie-breaker. If two pieces of information contained within the contract conflict, people can look to the contract precedence clause to point them toward which one to follow.
This way, if a dispute arises during a construction project because of contradictory or ambiguous information within the contract documents, all parties have clarity around which documents trump others. Ideally, this eliminates confusion and resolves any conflict.
Enumerating the contract document list in the precedence clause can deliver extra clarity. For example, the individual drawing up the clause might include the version number and date of the drawing package that takes precedence.
To provide a clearer idea of the order of precedence in construction contracts, examples of precedence lists help. Here are a few contract precedence clause samples.
In federal government work, the Federal Acquisition Regulation (specifically, FAR 52.215-8) governs the order of precedence to which contract documents apply. It says, “Any inconsistency in this solicitation or contract shall be resolved by giving precedence in the following order."
Representations and other instructions Contract clauses Other documents, exhibits, and attachments The specificationsThe Nebraska Department of Economic Development provides a Sample Construction Contract Provisions document. It states, “In the event of conflicts, the documents shall control in the following order of precedence.”
Contract with latest, Addenda, Amendments, or Change Orders Request for Proposal with latest Amendments Plans, Drawings and Specifications Contractor’s ProposalMichigan State University has published a version of the ConsensusDocs 200 Standard Agreement and General Conditions Between Owner and Contractor (Lump Sum Price). Section 14.2.5, the order of precedence clause, reads, “In case of any inconsistency, conflict, or ambiguity among the Contract Documents, the documents shall govern in the following order.”
Change Orders and written amendments to [this] Agreement Agreement and General ConditionsSubject to subsection 14.2.2 the drawings (large scale governing over small scale), specifications and addenda issued prior to the execution of this Agreement or signed by both Parties
Information furnished by the Owner pursuant to subsection 3.13.4 or designated as a Contract Document in section 14.1
Other documents listed in this Agreement. Among categories of documents having the same order of precedence, the term or provision that includes the latest date shall control. Information identified in one Contract Document and not identified in another shall not be considered a conflict or inconsistency.
Clearly, there are several approaches companies can take when applying contract precedence. The key thing to note is that a good contract precedence clause breaks the tie between two documents with competing or confusing information.
Setting an order of precedence in construction contracts — or providing some other way to resolve conflicting information — is always important. But certain types of construction contracts make this especially critical.
Ultimately, though, any good construction contract builds in a way to clear up issues when they arise.
Adding a contract precedence clause delivers the following perks for all stakeholders:
All of this said, not all projects use an order of precedence contract clause. That’s partially because some in the industry have moved away from this option to other ways to provide clarification.
Some leaders in the construction space, including the American Institute of Architects (AIA), now specifically advise against outlining order of precedence in construction contracts.
In Section 1.2.1 of its Guide for Supplementary Conditions, including Amendments to AIA Documents A201 and the Owner-Contractor Agreements, the AIA says, “In the event of inconsistencies among the Contract Documents, the Architect is to interpret them to reflect the design intent. Establishing a fixed order of priority is not recommended because no one document constitutes the best authority on all issues that may arise.”
When contract documents conflict, the stakeholder should move forward following whichever document lays out the highest standard specified in the contract. This clause hinges on clarity around which standard is higher, of course, so it’s not without its own issues.
Subscribe to Blueprint, Procore’s free construction newsletter, to get content from industry experts delivered straight to your inbox.
Ultimately, the order of precedence contract clauses and other similar clauses — like higher standard clauses — aim to resolve conflicts before they even begin by providing the requisite level of clarity. When companies have the bandwidth to do so, they can take a further step here.
To avoid conflicts that arise from a lack of contract clarity, companies can designate a person or team to harmonize the contract. Because the contract often contains documents from various teams — from legal to procurement to technical — having one dedicated pass-through of all of those documents together can help to discover (and ideally rectify) conflicts.
The best construction projects are the ones on which everyone wins. Creating construction contracts that provide clear direction helps all stakeholders, from the owner to the sub who’s on the jobsite for just one day, to move forward on the same trajectory with the same goal in mind.